Interface coordination during the construction phase
Water and electricity interface integration
Draw the locations of the main equipment and pipeline paths of the mechanical and electrical system of this project on a drawing, coordinate the overall configuration, ensure that all pipelines can be constructed and there is no conflict in elevation, and provide each subcontractor with the opportunity to develop their own construction and manufacturing drawings.
Structural and electromechanical interface integration
In order to coordinate with the installation of mechanical and electrical systems and take structural safety into consideration, the civil engineering project collects the opinions and requirements of the contractors for each project, and incorporates the required openings, foundations, casings, embedded objects, etc. into the structural/architectural drawings to provide reference for the contractors to draw construction/manufacturing drawings.
Coordination and integration of sub-item construction interfaces
Kunlun Construction is responsible for establishing a construction interface coordination plan network diagram based on time considerations for the "sub-item construction interface coordination plan" and reasonably arranging the construction sequence and schedule of the contractors so that each contractor can enter the site in order. In addition, each contractor should propose a construction and installation plan for the relevant work items, which will be compiled into a construction interface coordination plan after discussion and coordination as a basis for the coordination, handling and processing of the relevant interfaces.